Joint free slabs: construction checklist
Building Platform Preparation:
- Maintain slab thickness –
Ensure that the slab throughout is the specified
thickness "10mm
- Set out internal ground restraints
to suit the set out of the crack inducer grid, and
thereby avoid positioning crack inducer grid junctions
over ground restraints. Note that the crack inducer
grid should be set out as indicated on the drawings
to avoid cutting in around the perimeter.
- Remove all loose material
from the building platform, especially from the ground
restraints. Any crusher dust or the like used to level
the building platform must be compacted.
- Loosely fit the membrane
to all ground restraints and other surface depressions
to ensure the concrete will be in full and continuous
contact with the excavated surface. A light duty membrane
is preferred – 100 micron recommended.
JFS Grid Installation:
- Set out the crack inducer grid
as shown on the drawing to avoid cutting in around
the perimeter.
- Do not install the grid upside
down – The flat base of the crack inducer
grid junction is to lay directly on the ground and
the projections on the top are provided to restrain
the reinforcement mesh – refer to the detail
on the back.
- Install the grid in straight
lines to ensure the junctions are positioned
to provide proper support for the reinforcement mesh.
Note that the tubes are cut to length for a one metre
spacing of the junctions.
- Spike the junctions to
the ground every so often as necessary to prevent
the grid being inadvertently moved. Intermittent sheets
of mesh placed onto the junctions can also be used
for this purpose.
Placing of Reinforcement:
- Adjust laps in the reinforcement
mesh – Install the specified mesh reinforcement
using the lap details and staggered placement shown
on the drawing – refer also to the detail on
the back.
- Support mesh on grid junctions
– Ensure the sheets of mesh are supported
throughout on the grid junctions – refer to
the detail on the back. Note that the bars in the
mesh should always cross on the junctions if the sheets
are installed correctly. Marginally adjust the end
and side laps in the mesh as necessary to compensate
for any manufacturing discrepancies in the mesh sheets.
- Tie all end and side laps
in the mesh reinforcement.
- Install HD12 trimmer bars
as detailed on the drawings – refer also to
the detail on the back. Ensure all slab perimeters
in each pour, and all re-entrant corners and penetrations
are trimmed. Install bar chairs as necessary around
the perimeter and penetrations to ensure all trimmers
are adequately supported at the correct height.
Concrete Placement and Curing:
- 56 day drying shrinkage –
Order concrete with a 56 day drying shrinkage of 600
microstrain U.N.O.
- Dampen the ground immediately
prior to placing concrete in situations where there
is no membrane.
- Super plasticiser –
the use of super plasticiser is highly recommended
to increase workability and to assist with the control
of drying shrinkage.
- Prohibit the addition of water
to the concrete mix after any truck has departed the
batching plant.
- Compact all concrete using
mechanical vibrators.
- Cure all concrete for
seven days after placing and use aliphatic alcohol
as and if necessary during placing.
IF IN DOUBT, ASK!
|